| Range Path Work Continuing |
| Written by Jerry Richard | |||
| Wednesday, 14 December 2011 13:28 | |||
|
Winter hasn't arrived yet and the weather has allowed us to continue with outdoor work, specifically the range path. The fellas were busy the last couple of days loading in the gravel into the base of the path. The total cost of this project will be negligible in that the cost for the materials will be offset by the amount of reusable topsoil that was liberated from the path site. This topsoil will be used to complete tee decks on #2 and possibly elsewhere in 2012. It appears that the path itself will be ready to go come spring with another day of hauling and grading. The drainage contractors removed their equipment this week and are doing service work on it, but are counting on returning in the winter to do the drainage work on #11 if possible.
|